Thursday, April 28, 2016

LINE PRESSING & LINE DISPLACEMENT - 2 WAYS TO ENSURE PRODUCT LOSSES ARE MINIMISED.....Part 2

Dear Petrol Inspector,

Yesterday we started a series of 2 great ways to ensure petroleum product losses are minimised when discharging from vessel to shore tank farms.

We dwelt on Line pressing (packing) yesterday and today we shall deal on Line Displacement.

Ideally, this procedure is carried out when:

1. Integrity of the line in terms of pressure check is not guaranteed;
2. Line contains a different grade of product;
3. Line contains water;

PROCEDURES FOR LINE DISPLACEMENT METHOD
  • The vessel should be on an even keel with no list.  Otherwise, a     trim or list correction should be applied and noted on the report.  If a wedge calculation is necessary, then apply.

Note: Even-keel measurements are preferred because of the precision limitations involved in trim, list and wedge calculations.
The vessel quantity survey should be conducted prior to line displacement.

  • The number of vessel tanks used for line displacement should be minimized, and their location should be selected to minimize changes in trim or list. Deck lines, risers, bottom lines, and drop lines should be in the same fill condition both before and after line displacement between vessel and shore.
  • Agree on the quantity to be displaced or duration for the displacement.
  • It has been observed from experience that most inspectors will say "...discharge for 1hr". However, shore facility distances vary - hence quantity and duration for displacement will vary.
  • TOV of product displaced should be at least 120 percent of the combined capacity of all designated vessel and shore transfer lines. 
  • Agree on the cargo flow rate.
  • Line fill differences should not be addressed independently of the overall voyage analysis of the entire cargo transfer.


To apply the line displacement method, perform the following steps consecutively

Step 1 - Gauge and measure the temperature of delivering and receiving tanks before line displacement.  Measurements may be taken using either automatic measurement equipment or manual measurement equipment.

Step 2 - Transfer the volume required for displacement between vessel and shore.  Re-gauge the vessel and shore tanks using the same types of equipment and technique that were used for the opening measurements.

Step 3 - Using shore and vessel tank calibration tables, convert the measurements taken before and after line displacement to volumes.  TOV should be used to quantify volumes transferred.

Step 4 - Compare measured volumes of delivering and receiving tank(s) to determine whether their difference exceeds the agreed tolerance.  If vessel and shore volumes differ by more than the agreed tolerance, any or all of the following options may be exercised until all parties agree that line fullness has been determined to their satisfaction:

- Check all calculations for accuracy.
- Re-gauge shore tank (or verify its meter reading) and re-gauge designated vessel tank(s).
- Re-gauge all vessel tanks and reconfirm vessel line condition.
- Repeat the line displacement procedure.
  • Proceed with cargo transfer and determine after transfer whether the line fill difference has had any unacceptable effect on the cargo transfer volume.  

The initial line displacement volume will normally be part of the cargo transfer and must therefore be accounted for in the total transferred quantity.

Step 5 - For purposes of line fill determination, the designated pipeline system may be considered full if the difference between measured volume delivered and measured volume received is within the agreed tolerance.


Note: This does not necessarily ensure that voids do not exist in the line.

Till then - Keep inspecting properly!

Wednesday, April 27, 2016

LINE PRESSING & LINE DISPLACEMENT - 2 WAYS TO ENSURE PRODUCT LOSSES ARE MINIMISED

Dear Petrol Inspector, 

Today, let us look at 2 great ways to ensure petroleum product losses are minimised when discharging from vessel to shore tank farms. They are Line Pressing and Line Displacement.

Let us start with Line Pressing.

1. Line Pressing: Another common name for this is Line packing. This procedure assumes that the designated pipeline system is tight and able to withstand pressures applied during line press operations without loss of line pressure as determined by pressure readings from a calibrated pressure gauge from the vessel. This procedure is invalid with any pipeline system that does not meet this tightness recommendation. To apply the line press method (or the line pack method), perform the following steps consecutively. 

Step 1 - Close the valve at the shore tank. Open the vessel's manifold, COT tank (better just one) and pump valves, and gauge the tank before line press. Measurements may be taken using either reliable automatic gauging equipment or manual measurement equipment. 

Step 2 - Start the pump and run it until the discharge pressure stabilizes and/or reaches a predetermined pressure. The predetermined pressure should be higher than the maximum static pressure available on the system. 

Step 3 - Isolate the pipeline to prevent backflow and stop the pump. 

Step 4 - Once the pump has been shut down. record the pressure and re-gauge the COT using the same gauging method as that used for the opening measurements. Record the tank product level. 

Step 5 - If the tank product levels before and after the line press are within 1/8th inch (0.003 meters) of one another, pipelines may be considered liquid-full and no correction is necessary. 

Step 6 - If the COT liquid levels before and after the line press differ from one another by more than 1/8th inch (0.003 meters), relieve the line pressure into the tank until the pressure at the highest elevation is slightly above product vapour pressure and then repeat the test. If the tank product levels before and after the second line press differ from one another by less than 1/8th inch (0.003 meters), pipelines are now full of liquid because condensible vapours have been re-liquified and no further correction is necessary. 

Step 7 - If the tank liquid levels before and after the second line press differ from one another by more than 1/8th inch (0.003 meters), either the line fill condition may be corrected or - with the agreement of all parties - gas volumes may be estimated by procedures and calculations. 

Step 8 - For purposes of line fill verification, the designated pipeline system may be considered full if the difference between the volume gauged before line press and the volume gauged after line press is within measurement precision. Note: This does not ensure that voids equal to compressed gas volumes less than measurement precision do not exist in the line.

Now let me give you time to digest this. We shall talk about the Line Displacement tomorrow. 

Till then - Keep Inspecting properly!

Tuesday, April 26, 2016

We are Back - Bigger and Better!

Hi Fellow Inspectors, We have been away too long The Petroleum Inspector ought to be an expert in measurement and monitoring of petroleum products (like PMS, DPK, Crude oil etc) either being transferred via STS or ship to shore or vice versa. He/she is in control of millions of dollars worth of product, but most times paid peanuts. One of the reasons this happens is that the Surveyor is either poorly experienced or is not a professional. Over time, we shall be getting infos on various ways to get more professional and enhance avenues for Surveyors or prospective surveyors to get increased experience. So welcome back to this blog as we sail into proper petroleum products monitoring, in other to make good money!